The Kouga Wind Farm construction process is on track.  We are currently finishing off the earthworks and civil works for the WTG foundation bases.  To date, 27 of 32 turbine foundations have been completed. The substation gantries and transformer bay are also currently under construction. Note the wind turbines will only start arriving on site the end January/ early Feb 2014.