District road maintenance ongoing

As part of our infrastructure development the KWF project team is continuously maintaining and upgrading, at our cost, the main access road between St Francis Bay, Oyster Bay and Humansdorp.  Part of this upgrading works includes the stream crossing structure that is currently being improved as well as the placing of proper road quality gravel […]

Construction on track

The Kouga Wind Farm construction process is on track.  We are currently finishing off the earthworks and civil works for the WTG foundation bases.  To date, 27 of 32 turbine foundations have been completed. The substation gantries and transformer bay are also currently under construction. Note the wind turbines will only start arriving on site […]